Gravel: from driveway dimensions to a supplier order
Work from dimensions to cubic yards and weight, choose a supplier-specific bulk density, and keep material allowances separate from compaction.
Start with the layer you are measuring
Measure the length, width and thickness of one rectangular material layer. If the driveway has several sections or different depths, calculate each section separately and add the quantities. A single average depth can hide a much deeper area that needs extra material.
For US dimensions, cubic yards equal length in feet × width in feet × depth in inches ÷ 324. For metric dimensions, cubic metres equal length in metres × width in metres × depth in centimetres ÷ 100. These are geometric volumes, before any extra material allowance.
Density connects volume and weight
A cubic yard describes space; a ton describes weight. This calculator uses US short tons in US mode and metric tonnes in metric mode. They are different units. NIST defines a US short ton as 2,000 pounds, about 907.185 kilograms; a metric tonne is 1,000 kilograms.
Ask the supplier for the bulk density of the actual aggregate being delivered, in matching units. The example density in the calculator is editable. Vulcan Materials also treats density as an input in its own aggregate estimator, rather than using one universal number for every product.
Follow a complete worked example
A 40 ft × 12 ft layer at 4 in deep has a geometric volume of 5.93 yd³. A 10% extra allowance raises the planning volume to 6.52 yd³. At an example density of 1.4 short tons per yd³, the estimated order weight is 9.13 short tons. These figures are rounded for display; the calculator keeps more precision internally.
At an illustrative material price of $55 per short ton, the material subtotal is about $501.93. Delivery, tax and any other supplier charges need their own values. This example demonstrates the calculation; it is not a local price quote.
Check the order with your supplier
An extra percentage is a purchasing allowance, not a verified compaction factor. If your measurements describe a finished compacted layer while the quoted density describes loose aggregate, ask the supplier how to relate those conditions before ordering.
Keep base and finish layers as separate estimates when they use different materials. Confirm the final quantity, rounding or minimum delivery, access for the truck and delivery charge. The calculator estimates material quantity; it does not select a pavement design or determine drainage requirements.