Concrete Slab Cost Calculator
Estimate a rectangular slab in cubic yards or cubic metres. Compare ready-mix with bagged concrete and build a budget from your own prices.
How the calculation works
The slab volume comes from length, width and thickness. The allowance increases the volume before calculating ready-mix quantity or bag count. It is an explicit purchasing margin, not a recommendation for slab design.
Ready-mix cost uses the required order volume and your price per cubic yard or cubic metre. Actual suppliers may have minimum orders, order increments, short-load charges and pump fees. Add known fixed charges and verify the final quantity directly.
Bag mode divides the required volume by the product’s mixed yield and rounds up to whole bags. The initial 0.60 ft³ yield is an example from the QUIKRETE 80 lb Concrete Mix data sheet. Other bag sizes and formulations can have different yields.
Labor is entered per unit of slab area and excluded from the calculator’s tax basis. The optional tax rate applies to material plus the fixed delivery charge. This is a budgeting convention you can review against your actual quote.
Order volume = volume × (1 + allowance ÷ 100)
Bags = round up(order volume in ft³ ÷ mixed yield per bag)
Cost = concrete + labor + delivery + entered material/delivery tax
A worked example
A 12 ft × 10 ft slab at 4 in thick contains 40 ft³, or 1.48 yd³. A 10% allowance brings the order to 44 ft³, or 1.63 yd³. At 0.60 ft³ per bag, round 73.33 up to 74 bags. At an illustrative $160/yd³, ready-mix material costs $260.74; at an illustrative $7 per bag, 74 bags cost $518. These are input examples, not market prices.
Common questions
Why are bags rounded up?
You need whole purchasable bags. The tool applies the allowance first, divides by the bag’s mixed yield and rounds upward. It also shows the volume supplied by that rounded bag count.
Does every 80 lb bag yield 0.60 cubic feet?
No universal yield is assumed. The default is a specific QUIKRETE Concrete Mix example. Read the yield printed on your selected product and edit the field.
Are delivery and labor included?
They are included only when you enter them. Both start at zero. The displayed tax applies to concrete plus the entered fixed delivery charge; labor is excluded from this simplified tax calculation.
Does this calculator tell me how thick a slab must be?
No. Thickness is an input from your project specification. Required thickness, strength, reinforcement and subbase depend on the site and intended load.
Advertisement space